Some past and present Hitech projects:
Nigerian Defence Academy
Client: C & C Construction (another Chagoury Group company)
Domestic contractor on earthworks for roads and drainage; asphalt works to roads and parking for a surface area of 82,200m2. Surface dressing to walkways and roads for an area of 30,000m2.
The Nkweogwu Ring Road Unuahia North L.G.A.
Client: Abia State Government
The project included the rehabilitation and asphalt overlay including drainage of an area of road totalling 83,200m2.
Omoba - Umulkia Junction Road in Isiala Ngwu South L.G.A
Client: Abia State Government
The project includes rehabilitation and asphalt overlay including drainage (total area of road 65,700m2.)
Site Preparation Works for new Greenfield Brewery Enugu
Client: Nigerian Breweries Plc
The project involved site clearance of dense trees and bush, bulk earthworks of approx. 220,000 m2, drainage and roadworks.
Construction of Swali Bridge at Yenagoa Bayelsa State
Client: Bayelsa State Government
The project involved insitu concrete deck on precast concrete beams on piers with steel cased concrete piles, with a carriageway of 7.30m width inclusive of all sundries and extensive approach works.
|
|
|
|
|
|